Building making good progress

Thursday, October 15th, 2015

Our luxury apartments are starting to come together.

The final concrete pour on the roof of the 22 storey tower will be taking place at the end of November. This will complete the concrete frame of the building.

Cladding is progressing up the building and has reached the 6th floor. Work is due to commence shortly on the roof garden.

All of the gas, water and electricity supplies are now connected which will allow testing of all services to take place.

Final completion checks are taking place on the first flat and when complete the others will follow on in sequence.

Project Director, Paul Willis said:, “Construction is progressing very well and the quality being achieved by the contractor, Midgard, is excellent.